Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Get

1 - Find a drawing of the facility or make one if

a drawing is not available
  1. Mark location of the loggers, following the guidelines
  2. Mark location of the gateways, following the guidelines

you cant find it

2 - Mark on the drawing where measurement loggers

shall

should be placed

3 - Mark on the drawing where the

gateway

gateways should be placed, following the guidelines

4 - Check

cellular signal strength

for cellular connection where the gateways should be placed

5 - Check for electricity where the gateway

shall

should be placed

6 - Let

an

a electrician install power sockets

where gateway will be placed (

next to the gateway, if needed

)

Install

7 - Fasten the gateway, following the guidelines

, and turn it ON

8 - Turn the gateway ON and check if it has connected to the Controlant data cloud

9 - Mark the gateway ID number on the facility drawing

Install

10 - Distribute and fasten the measurement loggers, following the guidelines

11 - Mark

the location of the loggers

on the facility drawing

with

the loggers ID number and

the storage

location description (shelf

location

number etc.)