  1. Get a drawing of the facility or make one if a drawing is not available
    1. Mark location of the loggers, following the guidelines
    2. Mark location of the gateways, following the guidelines
  2. Mark on the drawing where loggers shall be placed
  3. Mark on the drawing where the gateway should be placed
  4. Check cellular signal strength where the gateway shall be placed
  5. Let an electrician install power sockets where gateway will be placed (if needed)
  6. Install the gateway, following the guidelines, and turn it ON
  7. Mark the gateway ID number on the drawing
  8. Install the loggers, following the guidelines
  9. Mark the location of the loggers on the drawing with the ID number and the storage shelf location number